Contractual Penalty for Delay in the Completion of Works – Why Is Taking-Over Important?

Construction contracts often provide for a contractual penalty if the contractor fails to complete the works within the agreed deadline.

However, the fact that a contractual penalty has been agreed and that the works have been completed after the contractual deadline does not necessarily mean that the employer will be entitled to claim it. To preserve this right, the employer’s conduct when taking over the works is also important.

In this regard, the Serbian Law on Obligations prescribes that a creditor may not claim a contractual penalty for delay if it has accepted performance of the obligation without notifying the debtor, without delay, that it reserves its right to claim the contractual penalty. In other words, an employer who accepts the works without giving the contractor an appropriate notice may lose this right, even if the contractor was late in completing the works.

This consequence is also confirmed by the judgment of the Supreme Court, Prev 1497/2023 of 18 July 2024. In a dispute concerning the construction of a production facility, the Court upheld the dismissal of the employer’s claim for a contractual penalty because the employer had failed to reserve its right to claim the penalty when taking over the works.

  1. What Does “Without Delay” Mean?

This issue is particularly important where the taking over of the works and the preparation of the final account do not take place simultaneously, and the employer postpones addressing the contractual penalty until the subsequent settlement of mutual claims.

In this regard, in its judgment Prev 661/2023 of 17 June 2026, concerning the construction of a sports hall, the Supreme Court held that the time limit for notifying the contractor that the employer reserves its right to claim a contractual penalty starts running from the date of taking over of the works, rather than from the preparation of the final account. The Court also stated that, in practice, the requirement to act “without delay” is generally understood to mean a period of no more than eight days.

Nevertheless, although this is the most recent case law, this position should not be interpreted as establishing a general additional eight-day period within which the employer can safely assume that a subsequent notice will preserve its right to claim the contractual penalty.

Indeed, in its judgment Prev 1570/2023 of 30 May 2024, concerning the manufacture and delivery of industrial equipment, the Supreme Court adopted a stricter approach. The creditor had failed to reserve its right to a contractual penalty when the equipment was taken over, and the notice served on the following day was not considered sufficient by the Court to preserve that right. In the case at hand, even notices sent during the period of delay, i.e., before the taking over of the works, were considered insufficient.

Although the above decisions differ in their interpretation of what constitutes timely notification, they clearly demonstrate the risk of losing the right to a contractual penalty if the matter is postponed until the final account is prepared.

  1. How Should the Employer Act When Taking Over the Works?

In light of the above case law, employers are advised to expressly notify the contractor, at the time of taking over, that they reserve their right to claim a contractual penalty for delay in the performance of contractual obligations, and to ensure that such notice is recorded in the taking over report.

Merely stating that the works were completed after the agreed deadline does not provide sufficient protection, nor should the employer rely exclusively on notices of default previously sent to the contractor.

  1. What If the Contractor Refuses to Have the Notice Recorded in the Taking Over Report or to Sign a Report Containing Such Notice?

It follows from the statutory requirement that the reservation of rights must be communicated to the debtor that this constitutes a unilateral statement by the employer, which does not require the contractor’s consent. Therefore, the contractor’s refusal does not prevent the employer from preserving its right.

What matters is that the statement is communicated to the contractor in a timely and unequivocal manner, and that the employer is able to prove both its content and the time at which it was communicated.

The same applies where a seller refuses to record in the taking over report the buyer’s statement reserving its right to claim a contractual penalty for delay in the delivery of the subject matter of the sale and purchase agreement.

In such circumstances, the employer or buyer is advised to communicate the statement at the time of taking over, while seeking to have both the statement and the other party’s refusal recorded in the report.

If this is not possible, the statement should be sent to the contractor on the same day by registered mail to its registered address for receipt of mail or, if no separate address for receipt of mail has been registered, to its registered office.

If such delivery is unsuccessful, the letter should be sent again, ensuring that at least 15 days elapse between the two mailings. Pursuant to the Serbian Companies Act, delivery shall be deemed duly effected upon the expiry of eight days from the date of the second mailing.

It should be noted, however, that this delivery procedure does not replace the timely communication of the statement reserving the right to a contractual penalty, nor does it extend the time limit for giving such notice. For this reason, it is important that the statement be communicated at the time of taking over and that appropriate evidence of such communication be secured.

At the same time, it is necessary to check whether the taking over report contains statements to the effect that all mutual obligations between the parties have been settled or that neither party has any further claims against the other. If such wording is included, the claim for a contractual penalty should be expressly excluded from any such statement, together with any other claims to which the employer or buyer does not intend to waive its rights.

Signing a taking over report without such a reservation may raise an additional question as to whether the employer or buyer has waived its claim, even where it has separately communicated that it reserves its right to a contractual penalty.

For contractors, on the other hand, the content of the taking over report and the related correspondence are important when assessing the merits of any subsequent claim for a contractual penalty.

Accordingly, the taking over process should be approached only after a prior review of the contract, applicable deadlines and relevant documentation, since the consequences of failing to give timely notice cannot necessarily be remedied by a subsequent final account or a later demand for payment of the contractual penalty.

Other news

News
ALTA banka’s bankruptcy and the implications for businesses

ALTA banka’s bankruptcy and the implications for businesses

Published: 2. 11. 2026.

The bankruptcy of a commercial bank is uncommon. When it occurs, however, the market quickly discovers that banks are not as solvent and liquid as expected. Its effects extend beyond the bank’s own clients to their customers and business partners who relied on the financial security the bank appeared to offer. For example, in Univerzal […]

Read more
News
New Classification of Activities – What Businesses Need to Know

New Classification of Activities – What Businesses Need to Know

Published: 6. 10. 2026.

A new Classification of Activities 2025 (“CA 2025”) will apply in Serbia as of 1 January 2027. Businesses will not need to submit any application or pay any fee for the alignment of their registered business activity. The Serbian Business Registers Agency (“SBRA”) will update the registered activity codes and descriptions ex officio. However, we […]

Read more
News
Annual Verification of Beneficial Ownership Data – First Deadlines from October 2026

Annual Verification of Beneficial Ownership Data – First Deadlines from October 2026

Published: 30. 9. 2026.

As of 1 October 2026, the first annual deadlines will begin to fall due for the review of beneficial ownership information recorded in the Central Records of Beneficial Owners maintained by the Serbian Business Registers Agency (“SBRA”). Under the Law on the Central Records of Beneficial Owners, registered entities are required to review the accuracy […]

Read more
SRBENG

Contact


If you have any questions or would like to schedule a consultation, please provide your contact details and we will get back to you as soon as possible. Alternatively, you can contact us directly by phone at: +381 11 4389 930